Skip to content
Call now +40 756 248 777

EU and PNRR irregularities for SMEs: inspections, corrections and defence

Author: · Published: · Updated:

What to check immediately

  1. What arrived: a document request, draft findings, recovery title, payment suspension or criminal procedural document.
  2. The programme and governing rules: PNRR has its own regime; other funds may fall under Emergency Ordinance 66/2011.
  3. Service dates and each defence deadline; an administrative challenge does not automatically stop recovery.
  4. Preserve original records and distinguish the company’s position from that of its director, consultant or supplier.

1. An audit report arrived: identify the document and its effect

An inspection may begin with a seemingly routine request: equipment invoices, competing quotations, publication evidence or a double-funding declaration. Organise the response before a missing record is treated as a missing transaction. Save the message, attachments, platform acknowledgement and receipt date. Identify the requesting authority, project and period. A file called an audit report does not necessarily have the same effect as a formal instrument establishing a repayable debt. The first task is to identify what the document actually decides, rather than responding only to its title.

Distinguish a preparatory document from an act that actually changes the beneficiary’s position. Check whether it identifies the debtor, amount, affected expenditure, reasons, payment deadline and remedy. Several instruments may need separate challenges: a recovery title, termination decision and payment suspension have different objects. A request for explanations is not automatically a timely challenge to the operative act. Challenging preliminary findings does not by itself preserve the deadline against a later recovery title. Keep the versions and delivery evidence together, so that each remedy can be attached to the correct act.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement.

2. PNRR and other EU funding: identify the correct legal route

For Romania’s National Recovery and Resilience Plan, inspection and recovery are governed principally by Emergency Ordinance 70/2022 and the institutional framework in Emergency Ordinance 124/2021. Other funding may fall under Emergency Ordinance 66/2011, depending on the programme and period. Correction scales, forms, security requirements and suspension rules cannot simply be transferred between them. Identify the component, investment, aid scheme, approved applicant guide and grantor in the financing documents. Describing an amount as EU money does not answer these questions or identify the correct defendant in litigation.

Where support is State aid or de minimis aid, also examine the scheme and the recovery instrument belonging to that regime. Article 10 of Emergency Ordinance 70/2022 refers those irregularities to Emergency Ordinance 77/2014; copying a procurement-correction challenge is insufficient. One company may face instruments with different legal bases. Identify the nature of each amount and its issuer before selecting the remedy. An explanation of PNRR inspections cannot replace examination of the individual aid scheme and the provisions governing its particular recovery decision.

Two separate dates matter. Article 3 of Order 372/2024 ties the procurement contract to the legislation in force when the notice launching the procedure was published. Article III(1) of Government Ordinance 3/2026 preserves the legislation in force at initiation for administrative irregularity and debt-establishment procedures already under way. An older file therefore needs a chronology of both procurement and inspection. The invoice date, contract-signing date or latest consolidation date cannot substitute for those distinct events. A current checklist is not proof that every earlier procurement was governed by its current wording.

The Facility’s overall timetable does not erase later controls. Article 20(5)(d) of Regulation (EU) 2021/241 sets the final milestone and target deadline no later than 31 August 2026, while Article 24(1) concerns payments to Member States by 31 December 2026. These dates neither extend an SME’s financing agreement automatically nor end record-keeping or recovery obligations. Check the individual project deadline and amendments. An expenditure item does not become eligible merely because payments under the Facility remain outstanding. Equally, completion of the project does not authorise disposal of its audit trail.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement; Government Emergency Ordinance 66/2011 — the separate regime for other EU funding; Order 372/2024 — temporal rules for private PNRR procurement; Government Ordinance 3/2026 — transitional rules for PNRR controls; Regulation (EU) 2021/241 — complementary funding, safeguards and timetable.

3. Who conducts the inspection and how to answer document requests

PNRR involves the national coordinator, reform and investment coordinators and, where applicable, implementing agencies or structures. A request does not necessarily come from a managing authority in the sense used by another programme. Articles 19–21 of Emergency Ordinance 70/2022 address inspection structures and situations where a coordinator is also a beneficiary. Ask which structure is acting, under what mandate, on which issues and for which records. A genuine competence objection should be reasoned and documented; it is not a general licence to withhold project records or prevent access.

Article 11(7¹) of Emergency Ordinance 70/2022 requires requested records to be supplied within 10 working days from the request. Identify the actual request and its delivery evidence; this is not the deadline for objections to draft findings. Use the required channel, an index, an explanation of each document and submission evidence. For an unavailable item, explain the reason, its custodian and the steps taken to obtain it. Asking for clarification or extra time does not itself extend the deadline. Keep originals intact and date any explanation prepared now accurately.

  • Organise the file by finding: rule invoked, transaction, evidence and affected amount.
  • Keep rejected offers, amendments and potentially adverse explanations as well as favourable records.
  • For electronic records, preserve the document and transmission acknowledgement; a screenshot alone may not explain the history.
  • Identify earlier inspections and their conclusions without assuming that previous approval prevents every later control.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement.

4. What must be established: an irregularity, missing evidence or fraud

An irregularity requires a link to a specific obligation and actual or potential damage to the protected funds; an inspector’s disagreement with a business choice is insufficient by itself. However, delivery of working equipment or a competitive price does not answer every transparency breach. Address both levels: the rule actually applicable and the effect on financing. A response stating only that the business worked hard or delivered a useful project may miss the legal reason for the correction. The supporting evidence must address the allegation rather than merely restating the project’s value.

Article 9 of Regulation (EU) 2021/241 focuses double funding on the same costs. Two projects or sources do not automatically establish that an expenditure item was financed twice. Reconcile invoices, individual items, assets, periods, amounts requested and amounts actually received from each source. Distinguish the beneficiary’s own contribution from public funding. Conversely, a general declaration that no double funding exists is not a substitute for accounting evidence. Where one invoice contains different items, show the allocation precisely and identify any genuine overlap rather than concealing it.

For the do-no-significant-harm environmental principle, usually called DNSH, identify the investment’s requirements and relevant technical evidence. Competitive procurement has its own documentation and declaration requirements; point 5.8 of the annex to Order 372/2024 provides a project-level beneficiary declaration for direct purchases. A missing declaration and substantive failure to satisfy an environmental condition are different findings. A signed declaration also cannot cure products or works that fail the agreed conditions. State precisely which finding is disputed and which record establishes compliance, including any limitation in the evidence.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement; Methodology of 6 May 2026, approved by Order 654/2026; Regulation (EU) 2021/241 — complementary funding, safeguards and timetable; Annex to Order 372/2024 — procurement, declarations and verification checklist.

5. Private PNRR corrections in 2026: test the classification and amount

For private beneficiaries outside public-procurement legislation, Article 10¹ and Annex 13 to Emergency Ordinance 70/2022 provide individual financial reductions or corrections. These corrections are not administrative-offence fines and do not automatically benefit from a half-payment option. The methodology of 6 May 2026 requires factual description, correct classification and reasoning on gravity and proportionality. The instrument should connect the finding to the affected contract and expenditure rather than merely tick a checklist box. Check the version applicable to the inspection before applying the current amounts to an older procedure.

Annex 13 situationSpecified amountWhat to check
Artificial splitting; launch/result publicity breaches; unlawful criteria, points 1–4RON 5,000–10,000 for the individual situationFacts, applicable point, reasons for the amount and the specific aggregation rule.
Missing double-funding declaration, point 5RON 15,000–30,000The precise documentary duty, distinct from actual overlapping costs.
Failure to verify DNSH declarations, point 6RON 15,000–30,000Procurement type, required declarations and established facts.
Between two and three breaches from points 2–4, point 7RON 30,000The precise situation; not every three project errors fall within it.

Other breaches cannot be answered by inventing a penalty. Article 10¹(3) provides for proportionality or, where possible, the analogy envisaged by that paragraph, after checking the applicable provision and methodology. The chosen rule needs reasons; a universal 25% or 100% assertion is insufficient. Distinguish the correction, ineligible expenditure and money actually paid that can be recovered. Check earlier deductions and repayments. Different administrative or criminal labels do not establish several independent losses for the same expenditure. An accounting reconciliation helps identify the amount still genuinely in dispute.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Methodology of 6 May 2026, approved by Order 654/2026; Government Ordinance 3/2026 — transitional rules for PNRR controls.

Have draft findings or a recovery title arrived?

Prepare the complete instrument, service evidence, financing agreement and disputed expenditure records. The assessment and any representation require a separate legal-assistance agreement; sending documents does not automatically establish a mandate.

6. Objections to draft findings: make the first response specific

Under Emergency Ordinance 70/2022, draft findings are sent to the beneficiary for a response. Article 11(10) allows 5 working days from receipt of the draft for written objections. Preserve receipt evidence, number the findings and answer each separately. Attach existing relevant records rather than an unexplained mass of files. Identify what the inspection omitted and why that omission affects the conclusion. Failure to object is not a criminal confession, but can leave the administrative account unanswered. Do not assume that later litigation will make the short draft-response deadline irrelevant.

For an allegedly restrictive specification, a useful response may address compatibility, required performance and real alternatives available when procurement began. Points 6.1 and 6.3 of the procurement rules require consistent assessment of offers; a later explanation cannot rewrite criteria to favour the winner. For publicity, examine platform history and the information actually accessible. Failure to publish differs from an inspection overlooking an existing publication. Technical explanations need technical evidence, not only legal language. Where a genuine breach occurred, an honest account of its scope is stronger than a denial contradicted by the project file.

A reconciliation meeting may clarify disagreements, but Article 11(11) does not make it a guarantee that the beneficiary’s view will be accepted. Ask for a record of the issues discussed and a reasoned answer to decisive evidence. Where the suspicion is unconfirmed, or confirmed without financial impact, Article 11(12¹) and Annex 11 provide for a closing note. Clerical or arithmetic errors have the rectification route in Article 12(2) and Annex 10. A rectification request is not a substitute for a challenge to the substantive lawfulness of recovery and does not automatically preserve its deadline.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Annex to Order 372/2024 — procurement, declarations and verification checklist; Methodology of 6 May 2026, approved by Order 654/2026.

7. The recovery title: challenge and payment deadlines are separate

For a PNRR recovery title, the administrative challenge goes to the issuing authority within a maximum of 30 calendar days from service, on pain of forfeiture: Article 14 of Emergency Ordinance 70/2022 and Article 33 of Emergency Ordinance 124/2021. Do not substitute a 45-day period encountered for other tax instruments. Identify the title, disputed amounts and measures, reasons, evidence and signature of the entitled person or authorised representative. The administrative challenge is not subject to stamp duty. Check the actual means of service, including qualified electronic documents, rather than treating the issue date as receipt.

Article 15 provides a request to complete missing information within 5 days from notification; this is not a fresh deadline for lodging any otherwise late challenge. Article 17 requires a reasoned decision and permits full or partial cancellation and, where appropriate, a replacement title within the decision’s reasons. Attach a calculation of the disputed difference and ask for an answer to each finding. Deliberately identify the scope of a partial challenge: disputing one invoice does not automatically place every recovery item before the authority. Keep proof of submission and any request for completion with the original service record.

StepPNRR period and triggerDistinct from
Requested inspection records10 working days from the request, Article 11(7¹)Response to draft findings.
Objections to draft findings5 working days from receipt, Article 11(10)Challenge to the final title.
Administrative challengeMaximum 30 calendar days from service of the titlePayment period and suspension request.
Payment of the debt30 days from service of the titleAutomatic suspension through a challenge.
Decision on the challenge30 days from registration/completion; reasoned stays may applyAutomatic acceptance if the response is late.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement.

8. Three different stays: establishment, challenge and enforcement

A criminal referral does not mechanically halt all administrative activity. Article 12(6) permits continued inspection and, where appropriate, establishment of the debt if the determination is not affected. Article 13(10) addresses suspension of issuing the title where the debt’s existence depends on a criminal act and its conditions are met. Article 17(2) concerns a different stage: a reasoned stay of the administrative challenge where a criminal determination or another judicial dispute is decisive. Ask which condition is met and which formal decision was made; the existence of a criminal file alone is not the complete analysis.

Suspending enforcement means stopping enforceable effects, not merely postponing the administrative answer. Article 33(5) of Emergency Ordinance 124/2021 expressly states that an administrative challenge does not suspend the title’s enforcement. A judicial application must establish a well-justified case and imminent damage under Law 554/2004, supported by evidence of the business’s actual position. For funding governed by Emergency Ordinance 66/2011, Article 50(9) also contains a security rule of up to 20%; that provision is not automatically copied into every PNRR dispute. Identify any applicable special requirement before budgeting the application.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement; Government Emergency Ordinance 66/2011 — the separate regime for other EU funding; Administrative Litigation Law 554/2004 — courts, time limits and suspension.

9. Judicial proceedings: the competent court and the case file

The administrative decision may be challenged before the administrative court. Identify both that decision and the underlying title whose cancellation is sought, together with the precise amounts and relief. Law 554/2004 generally provides six months from service of the answer or expiry of the statutory response period, depending on the applicable situation. Its exceptional extension for sound reasons is not an ordinary one-year deadline, and an unanswered challenge should not be left indefinitely. A lawful stay of the administrative procedure requires the separate analysis in Article 11(2¹). Establish the trigger using evidence, not an assumed delivery date.

For acts concerning amounts of non-repayable EU funding, Article 10(1¹) uses a value criterion: the RON 3,000,000 threshold distinguishes the tribunal from the court of appeal. Non-monetary acts are assessed by the authority’s rank, and a repayable component is not automatically a grant. A private company must also consider exclusive territorial jurisdiction at its registered office under paragraph (3). Determine competence for the actual claim; the fact that the issuer is a ministry does not by itself settle every EU-funding dispute. A wrongly selected court can create delay even where the underlying objection is substantial.

Coordinate interim suspension with cancellation proceedings. Article 14 requires the cancellation action within 60 days from the suspension application, with the consequences stated there if the deadline is missed; the general six-month period cannot be relied on to preserve that interim protection. Article 15 permits a suspension request with the main action or separately within 60 days from bringing it. The suspension decision has a five-day appeal on points of law from service, without that appeal suspending the decision. The merits judgment generally has a separate 15-day appeal on points of law from service.

If the challenged instrument is a fiscal administrative act, check the special provision before applying the general timetable. Article 278(5) of the Code of Tax Procedure links cessation of suspension to failure to bring cancellation proceedings within 60 days from service of the administrative challenge decision. Do not assume every PNRR recovery document automatically has that classification. The distinction may also affect security and coordination of the merits deadline. Explain why the selected regime applies, using the instrument’s nature and special provisions, rather than merely the fact that a tax body ultimately enforces the debt.

For assessment of jurisdiction, evidence and urgent measures, see the litigation assistance and representation service. The mandate and the cost of the work are agreed separately.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement; Administrative Litigation Law 554/2004 — courts, time limits and suspension; Romanian Code of Tax Procedure — limitation and suspension of fiscal acts.

10. Suspended payments, recovery and interest

Inspection, withholding a future payment and recovering money already paid are different operations. Article 31(10) of Emergency Ordinance 124/2021 regulates, on its conditions, payments up to initiation of the criminal action and the guarantee instrument required for the beneficiaries concerned. Paragraph (11) concerns payment suspension following the prosecutor’s referral for trial, for the identified economic contract. Financing clauses may provide a distinct suspension basis. An administrative challenge does not itself compel the authority to continue every payment. Identify the decision, contractual clause and procedural event actually relied on before seeking reversal or payment.

Interest and enforcement can follow maturity. Article 13 of Emergency Ordinance 70/2022 and Article 32 of Emergency Ordinance 124/2021 distinguish principal from the separate instrument establishing interest. Verify the balance, maturity, payments and National Bank of Romania reference rate at the statutory date; do not automatically substitute the daily rate applicable to a different tax debt. Where collection fails, enforceable titles and service evidence may be sent to the competent tax bodies. The inspection authority and the body implementing enforcement are not necessarily the same institution at every stage.

Do not calculate limitation for establishing the claim simply as five years from signing the financing agreement. Article 31(18) of Emergency Ordinance 124/2021 refers to Article 110(1) of the Code of Tax Procedure, which provides five years unless otherwise prescribed by law; Article 13(9) of Emergency Ordinance 70/2022 must be considered alongside interruption, suspension and applicable EU rules. Establishment and enforcement have separate chronologies. A limitation argument requires proved dates and acts and analysis of the relevant provisions. The project’s age alone is insufficient, and the end of implementation is not automatically the starting point for every recovery period.

Sources and legal provisions: Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement; Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Romanian Code of Tax Procedure — limitation and suspension of fiscal acts.

11. When the administrative problem also raises criminal issues

An audit report is not a conviction and does not automatically make a director or consultant a defendant. That status follows initiation of the criminal action, not only referral for trial. Articles 18¹–18³ of Law 78/2000 have their own conditions concerning documents, omitted information, result and use of funding; Article 18⁵ separately addresses negligence by a person with decision-making or supervisory duties in its defined situation. Identify who prepared, checked, signed and submitted each record, what they knew and their duty. Paying a correction does not automatically terminate criminal proceedings or establish guilt.

Jurisdiction does not follow solely from the funding logo. Articles 22 and 25 of Regulation (EU) 2017/1939 govern the European Public Prosecutor’s Office’s competence and its exercise. Damage below EUR 10,000 to the Union’s financial interests has specific conditions and exceptions; the EUR 10 million threshold for certain cross-border VAT offences is not a general grant-fraud threshold. Article 6 of Emergency Ordinance 70/2022 distinguishes referral to the European Public Prosecutor’s Office, information to Romania’s Fight against Fraud Department and other referrals. Not every irregularity must be investigated by the National Anticorruption Directorate.

For the conditions of an accusation and the beneficiary’s or consultant’s role, continue with the separate guide to fraud involving EU funds. This article focuses principally on the SME’s response to inspection and recovery.

Sources and legal provisions: Law 78/2000 — offences against the Union’s financial interests; Romanian Code of Criminal Procedure — procedural status and asset restraints; Regulation (EU) 2017/1939 — competence of the European Public Prosecutor’s Office; Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims.

12. Frozen accounts: criminal restraint is not enforcement of the recovery title

Obtain the instrument causing the freeze, secured amount, assets and purpose. Criminal restraint preserves assets; it is not final confiscation of the money. Article 249 of the Code of Criminal Procedure distinguishes affected people and property according to whether the purpose is a fine, confiscation, costs or compensation. The company and director are not the same owner. Provide repayment evidence and request assessment of the remaining amount and proportionality. Repayment does not itself lift every restraint, particularly one serving more than one statutory purpose. Identify the authority that can decide the requested change rather than addressing every request to an asset administrator.

Criminal time limits are short and separate. Current Article 250(1) provides three days from service of the prosecutor’s order; implementation of a judicial restraint has the separate situation in paragraph (6). Article 250¹ concerns the 48-hour challenge from pronouncement or, where applicable, service of a judicial decision on imposing restraint. Those challenges do not suspend execution. Do not wait for a 30-day administrative challenge to protect accounts in a criminal case. A later request to narrow restraint is not automatically a substitute for the initial challenge or a way to revive a missed deadline.

For the relevant instruments and remedies, see the guide to asset restraint in European Public Prosecutor’s Office cases. Narrowing restraint remains a different question from cancelling a financial correction.

Sources and legal provisions: Romanian Code of Criminal Procedure — procedural status and asset restraints.

13. Records and official forms: what to preserve and what needs adaptation

Article 35(2) of Emergency Ordinance 124/2021 requires records to be kept for ten years from the end of the financial year in which the last payment was made. Paragraph (4) separately requires records connected to audits, litigation and investigations to be retained until those matters end. Do not destroy them after a favourable initial inspection. Keep offers, valuation justification, selection report, contract and amendments, acceptance, payments, asset records and correspondence. Copies and electronic files must preserve version history and allow authenticity to be checked; a newly reconstructed spreadsheet should be identified as a reconstruction, not passed off as an original.

Official sources contain different instruments. Annex 7 to Emergency Ordinance 70/2022 is the authority’s correction-note model; Annexes 10, 11 and 12 concern rectification, closing a suspicion and cancelling a title. Within the annex to Order 372/2024, Annexes 1–2 provide indicative declarations, Annex 3 lists the procurement file and Annex 4 is the verification checklist. A beneficiary cannot issue an authority’s cancellation decision. The applications below are original drafting models, not official forms or ready-to-file documents. Select the correct addressee, legal regime, evidence and requested decision before using any of them.

References to Financial Regulation 2018/1046 should neither be mechanically deleted from an older agreement nor presented as the sole current rule. Financial Regulation 2024/2509 repeals it, but Article 277(4) preserves earlier rules for legal commitments entered into before the new regulation took effect. Identify the commitment and transitional rule when framing a legal ground. An older reference may require that explanation; it does not by itself establish that the entire financing agreement or inspection has no legal basis. Current rules and the law applicable to an earlier commitment must be distinguished.

Sources and legal provisions: Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement; Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Annex to Order 372/2024 — procurement, declarations and verification checklist; Financial Regulation (EU, Euratom) 2024/2509 — transition and repeal.

14. Original applications and submissions for specific situations

Replace bracketed fields only with verified facts, select grounds supported by the file and remove unsupported requests. Do not complete a declaration on honour by guessing. These models are not designed for simultaneous submission to every institution: an inspection request, administrative challenge and judicial application have different addressees and conditions. The company’s competent representative or authorised lawyer must sign for it. Check the mandate and any conflict with the director’s personal defence. An English explanation of a model does not establish that an authority accepts an English-only filing.

Model 1 — Indexed documentary response and clarification of scope

Model 2 — Objections to draft findings

Model 3 — Double-funding reconciliation submission

Model 4 — Submission on the correction amount and proportionality

Model 5 — Administrative challenge to a PNRR recovery title

Model 6 — Request concerning an audit recommendation withdrawn in the final report

Model 7 — Request for reasons and scope of an administrative stay

Model 8 — Structure of a judicial suspension application

Model 9 — Reconciliation of recovery and interest

Model 10 — Application to assess narrowing a criminal asset restraint

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Annex to Order 372/2024 — procurement, declarations and verification checklist; Romanian Code of Criminal Procedure — procedural status and asset restraints.

15. Frequently asked questions

Can a functioning project still attract a correction?

Yes. Delivery and use do not automatically answer a procurement or eligibility breach. The applicable duty, facts and actual or potential financial impact must be examined. Equally, the project’s utility, actual competition and expenditure genuinely affected may be relevant to classification and proportionality. They should be evidenced rather than offered as a general excuse or ignored by the assessment.

Does a missing declaration prove double funding?

They are different findings. A documentary breach can have its own consequences under the applicable regime, while overlapping funding must be tested against the same costs. Produce existing declarations, requests, amounts actually received, accounting evidence and item-level allocation. Do not backdate a newly prepared declaration or present it as though it existed when procurement took place.

Is a PNRR correction a fine payable at half the amount?

Administrative-offence fine rules do not apply automatically. The individual financial correction and recovery debt follow the funding regime and instrument issued. The current private-beneficiary situations in Annex 13 have specified amounts and a particular rule for certain multiple breaches. Check the law applicable to the procedure and the actual calculation rather than assuming a reduced-payment discount.

Does filing a challenge stop recovery?

Not automatically. Emergency Ordinance 124/2021 expressly provides that an administrative challenge does not suspend the title’s enforcement. Judicial suspension requires its own application and statutory conditions. It differs from staying determination of the administrative challenge because of a decisive criminal issue, and from an authority withholding future financing payments. Identify the decision and relief actually needed.

Can I seek cancellation when the final audit report changes the finding?

Article 12(15¹) of Emergency Ordinance 70/2022 may apply where its conditions concerning withdrawn recommendations and a title based on draft findings are met. Supply both reports and connect the changed passages to each amount. Not every difference between draft and final reports automatically cancels all project liabilities, and the request is not a reason to miss applicable challenge deadlines.

Do the company and its director have the same defence?

Not necessarily. The recovery title may concern the beneficiary, whereas criminal risk requires individual assessment of conduct and roles. The company, director, consultant and supplier may share interests or face conflicts. Establish who represents the company, who has been summoned in criminal proceedings and each lawyer’s mandate before submitting a common account or treating one person’s admissions as the company’s position.

Must every irregularity be referred to the European Public Prosecutor’s Office?

No. Relevant indications and an assessment of competence under the applicable rules are needed. Article 6 of Emergency Ordinance 70/2022 distinguishes the situations, and Regulation (EU) 2017/1939 has its own conditions, including for damage below EUR 10,000. A missing record is not equivalent to a proved criminal accusation or universal jurisdiction of one particular prosecution structure.

Can I dispose of records when the project ends?

Do not assume so. The PNRR rule in Article 35(2) concerns ten years from the end of the financial year of the last payment, while audits, litigation and investigations carry additional retention duties. Check the financing agreement, aid regime and pending proceedings as well. Maintain controlled access and recoverable copies without altering originals or deleting inconvenient documents.

Sources and legal provisions: Government Emergency Ordinance 70/2022 — PNRR inspections and recovery claims; Methodology of 6 May 2026, approved by Order 654/2026; Regulation (EU) 2021/241 — complementary funding, safeguards and timetable; Annex to Order 372/2024 — procurement, declarations and verification checklist; Government Ordinance 3/2026 — transitional rules for PNRR controls; Government Emergency Ordinance 124/2021 — PNRR funding, payments, records and enforcement; Administrative Litigation Law 554/2004 — courts, time limits and suspension; Law 78/2000 — offences against the Union’s financial interests; Romanian Code of Criminal Procedure — procedural status and asset restraints; Regulation (EU) 2017/1939 — competence of the European Public Prosecutor’s Office.

Coordinate the administrative and criminal response around the actual instruments

For a useful discussion, prepare the service chronology, instruments received and an evidence index. Assessment of the challenge, a suspension application and any criminal defence have separate scopes and costs agreed through a separate legal-assistance agreement. Outcomes depend on applicable law, evidence and the authority’s or court’s decision.

This material considers legislation and case law available up to 7 November 2026. The version applicable to the events or proceedings must also be checked for the particular case. This is general information.