Romanian PPAs: structuring, negotiation and risk allocation
Questions the agreement must answer
- What is being purchased: delivered energy, a profile or a financial difference?
- Who bears shortfalls, imbalances, negative prices and grid curtailment?
- Which documents trigger delivery and payment?
- How do security, renegotiation and exit work in an adverse scenario?
A power purchase agreement, or PPA, can stabilise part of a project’s revenues or a buyer’s energy costs. It does not itself guarantee the lowest price, actual generation or project finance. We assist generators, industrial buyers, suppliers, traders and investors with structuring, drafting, negotiation, amendments and disputes. The commercial objective must be reflected in workable terms: who delivers what, during which intervals, supported by which records, and who pays when the expected business scenario fails.
Sources and legal provisions: Regulation (EU) 2019/943, consolidated text: PPAs, balancing and redispatching.
Choose the structure before negotiating the price
Article 2 point 77 of Regulation (EU) 2019/943 defines a PPA through the purchase of electricity from a producer on a market basis. The definition prescribes neither one mandatory ten- or twenty-year duration nor a restriction to newly built assets. The Commission’s 2026 Recommendation distinguishes physical and financial contracts. Under a financial structure, settling a difference against a reference price does not automatically supply the electricity needed by a factory: physical supply must still be arranged separately.
| Structure | Decisive question |
|---|---|
| Physical delivery | Are delivery point, scheduling, metering and balance responsibility aligned? |
| Financial settlement | What is the reference index, and what happens if it differs from the price actually paid for consumption? |
| Pay-as-produced | Who buys the shortfall when generation is lower, or occurs in different hours from demand? |
| Fixed profile or baseload | Who sources energy missing from the profile and sells any excess? |
| Intermediary or multiple buyers | How are roles, costs, security and the effects of one participant’s exit allocated? |
In an intermediary structure, that party may handle scheduling or top-up electricity for a fee. Saying it “handles everything” is insufficient: separate the generator’s duties, the intermediary’s service and the buyer’s agreement. For a financial PPA, assess instrument classification and financial-regulatory, accounting and tax implications with the relevant specialists. The commercial label “virtual” does not certify an exemption or replace a document-based assessment.
Sources and legal provisions: Regulation (EU) 2019/943, consolidated text: PPAs, balancing and redispatching; Recommendation (EU) 2026/917: PPA barriers and structures.
Documents and review deliverables
For the initial review, provide the offer and term sheet, the draft with every schedule and amendment, party details and licensed roles, project records and connection status. We need generation and consumption profiles at relevant intervals rather than annual totals alone, financial assumptions, lender requirements and proposed security. An existing dispute also calls for notices, meter data, invoices and system-operator instructions. An unconfirmed technical assumption must remain identified as such instead of silently becoming a contractual warranty.
- Structure sheet: energy, profile, duration, delivery point, price, counterparties and linked services.
- Risk matrix and commercial decision list covering favourable and adverse scenarios.
- Reviewed agreement and schedules with tracked changes and explained comments.
- Conditions-to-commencement checklist, security documents and notice calendar.
- Operating instructions for metering, settlement, reporting, evidence retention and escalation.
If the project faces a technical block, the PPA review must be coordinated with grid connection work.
Commencement conditions and project delay
Signature, effectiveness and first delivery may occur on different dates. List the required conditions: permits or licences for the relevant role, finance, connection records, tests, metering, security and balancing or supply arrangements. Identify who provides evidence, who reviews it, whether it may lawfully be waived and the final deadline. The agreement does not itself supply a missing authorisation or bind a system operator to a timetable it has not accepted.
Distinguish developer-caused delay, grid delay and administrative change. Decide whether they lead to an extension, temporary replacement supply, agreed damages or termination after a final longstop. Replacement electricity must be tested against any promised renewable attributes, not just its MWh quantity. A lender may seek notice and an opportunity to remedy before termination; these must be reconciled with buyer rights and the lifespan of the security.
Sources and legal provisions: Electricity and Natural Gas Law 123/2012.
A fixed price is not a guaranteed all-in cost
Draft the formula so both parties can reproduce it: currency, unit, index source, time zone, settlement interval, rounding, cap or floor, and missing-data treatment. Separate the energy price from shaping, balancing, intermediary services, network charges, taxes and guarantees of origin. If the index changes or disappears, define its replacement and how a disagreement is resolved. Where one party controls these inputs unilaterally, test the arrangement against an adverse market scenario for the other party.
An illustrative example: 100 MWh is financially settled against the difference between a fixed EUR 80/MWh price and a EUR 60/MWh index. The arithmetic difference is EUR 2,000, but who pays whom depends on the agreed sign convention, and the result does not determine the buyer’s physical-supply bill. If the index is negative, the formula must state whether it applies in full, is capped or suspends a volume. Negotiate negative prices and voluntary generation reductions separately rather than concealing either issue in a general force-majeure clause.
Volumes, forecasting, imbalances and storage
A solar generator may meet the annual estimate while failing to cover the hours when the buyer needs power. Define interval quantities, tolerances, forecasts, scheduling, shortfalls and excess. Identify who may source replacements, from where and at what cost. Storage adds losses, own consumption and movement of delivery between intervals; reflect those effects in metering and origin obligations without counting the same quantity twice for contractual benefits.
Article 5 of Regulation (EU) 2019/943 generally requires participants to assume balancing responsibility or delegate it contractually to a balance-responsible party. A clause allocating the cost between generator and buyer must fit that market relationship. For renewable installations commissioned from 1 January 2026, paragraph 4 narrows the capacity-based derogation to strictly below 200 kW. Article 21 of Romanian law retains below-400-kW wording for prosumers: commissioning date and the directly applicable EU rule must be considered together; the domestic threshold alone does not establish a general exemption.
Sources and legal provisions: Recommendation (EU) 2026/917: PPA barriers and structures; Regulation (EU) 2019/943, consolidated text: PPAs, balancing and redispatching; Electricity and Natural Gas Law 123/2012.
Have a PPA offer before signing?
The offer, profiles and proposed security reveal decisions that may change the actual cost. We can prepare comments and a negotiation sequence.
Curtailment and grid compensation
Separate a system-operator instruction for safety or congestion from plant failure and a commercial decision not to generate. For each category, define notice, records, estimation of undelivered energy and the effect on PPA performance. The operator’s instruction, timings, measurements and demonstrated availability matter more than a general “curtailment” label. Also establish whether connection rights are firm or permit restrictions.
Article 13(7) of Regulation (EU) 2019/943 concerns compensation for non-market-based redispatching and contains an exception where producers accepted connection without a firm-delivery guarantee. A claim against the system operator and agreed compensation between PPA parties are separate claims. State who seeks operator compensation, whether it must be passed on, what is deducted and how double recovery is avoided. Full hypothetical revenue recovery cannot be promised for every restriction.
Sources and legal provisions: Regulation (EU) 2019/943, consolidated text: PPAs, balancing and redispatching.
Security, finance and renewable attributes
Useful security must cover the actual exposure: current invoices, contract-value changes, replacement electricity or an agreed termination amount. Choosing a bank instrument, parent guarantee, deposit or conditional-release account depends on creditworthiness and enforceability. Check issuer, beneficiary, amount, currency, demand documents, expiry, renewal and release. A parent with the same financial problems may not reduce group risk. Nor should a bank instrument be assumed drawable for an event outside its wording.
“Bankable” means acceptable to a financier, not a universal legal certification. Negotiate assignment, agreed lender-intervention rights, cure before termination and any direct agreement without assuming a lender can automatically take over a licence. For renewable attributes, Article 73 of Law 123/2012 refers to guarantees of origin. Specify whether these are included, the quantity, period, holder and evidence of transfer or cancellation. Purchasing electricity and being entitled to make a particular sustainability claim require separate checks.
Sources and legal provisions: Electricity and Natural Gas Law 123/2012.
Change in law, force majeure and hardship
Where Romanian law applies, Article 1270 of the Civil Code starts from the agreement’s binding force. Article 1351 defines force majeure through an external, unforeseeable, absolutely insurmountable and unavoidable event, within the applicable statutory and contractual conditions. A price increase, a smaller margin or any administrative delay does not qualify automatically. Define the affected obligation, causal connection, notice, mitigation, accrued payments and consequences of a prolonged disruption.
Hardship under Article 1271 has different conditions: a subsequent exceptional change, excessively onerous performance, statutory unforeseeability, risk not assumed and a good-faith attempt at reasonable renegotiation. A court may adapt or end the agreement under those conditions; this is not a general unilateral right to stop delivery. A change-in-law clause separately defines covered changes, the reference date, net cost, evidence, renegotiation and the outcome if no agreement is reached. A producer invoking a new tax does not, by itself, transfer that tax to the buyer.
Sources and legal provisions: Romanian Civil Code: binding force, hardship, force majeure and penalties.
Exit, delivery zone and dispute evidence
Article 19a(7)–(8) of Regulation (EU) 2019/943 requires the delivery bidding zone, responsibility for cross-zonal transmission rights following a zone change, and exit terms including any fees and notice periods, subject to competition law. A cross-border PPA must address differences between the generator’s and consumer’s indices, currency and transmission rights. Confidentiality wording cannot be used to disregard a statutory reporting or disclosure obligation.
For default, define the breach, evidence, notice, cure period and the person entitled to terminate. A close-out formula must specify valuation date, replacement transactions, discounting, security and offsets. Where an amount operates as a contractual penalty under Romanian law, examine Articles 1538 and 1541 of the Civil Code, including reduction in the cases permitted by statute. Calling an amount an “exit fee” does not certify that reduction is impossible. Distinguish a calculation or metering expert from the court or tribunal deciding the legal dispute.
Sources and legal provisions: Regulation (EU) 2019/943, consolidated text: PPAs, balancing and redispatching; Regulation (EU) 1227/2011, REMIT, consolidated text; Romanian Civil Code: binding force, hardship, force majeure and penalties.
Reporting and updated EU rules
For transactions within REMIT, allocate data, identifiers, reporting, acknowledgements and corrections without assuming that delegation removes every participant obligation. Article 9 requires submission of the registration form before entering into a reportable transaction; a participant already registered in another Member State does not register a second time simply because it negotiates here. For third-country participants, also check the representative required under the current regime. REMIT registration and licensing for an energy activity serve different purposes.
Implementing Regulation (EU) 2026/256 repealed the earlier instrument from 29 April 2026, but Articles 16–17 temporarily retain certain old provisions and phase in new requirements in 2027 and 2028. Do not treat every new field and deadline as already applicable in November 2026. For each PPA, establish the category, transaction date, obligation and actual operational mechanism with the reporting lead. Legal analysis of the transition does not replace checking the technical format required for the individual report.
Recommendation (EU) 2026/917 of 22 April 2026 addresses smaller buyers, aggregation, guarantees and coordination with support schemes. It is a recommendation, not an automatic entitlement to a state guarantee or a contract. ACER’s PPA page lists voluntary templates and explains its assessment that additional templates are unnecessary. An industry model remains a starting point: it is not presumed mandatory, suitable under every governing law or a substitute for the project schedules.
Sources and legal provisions: Regulation (EU) 1227/2011, REMIT, consolidated text; Implementing Regulation (EU) 2026/256: reporting transition; Recommendation (EU) 2026/917: PPA barriers and structures; ACER: PPAs and the list of voluntary templates.
Our own request and contract-instruction examples
These examples are drafted for PPA negotiation and administration. They are neither ANRE-approved forms nor reproductions of EFET or ISDA text. Adapt them to the facts, party role and agreed clauses; using one of these headings does not allow a notice to amend the contract unilaterally. Insert dates and deadlines only after checking receipt and the contractual rule, and ensure the signatory has the necessary authority.
1. Request clarifying the offer and structure
For offer [identifier], please confirm whether the obligation is physical delivery or financial settlement, interval volumes and the bidding zone. Clarify the index, currency, shaping costs, balance responsibility and negative-price treatment. Our demand profile and assessed scenarios are attached. This request does not accept unresolved parameters or replace signing conditions; we propose a schedule distinguishing agreed points, reservations and matters requiring internal approval.
2. Confirming conditions to first delivery
Under clause [reference], we provide evidence for conditions [list] and identify those still outstanding. Confirm review, missing records and the proposed first-delivery date. For condition [identifier], we request an agreed extension to [date], expressly preserving other rights. This letter does not itself establish fulfilment or waive a mandatory authorisation. The chronology and actual programme impact are attached.
3. Metering and settlement reconciliation
We dispute items [invoices/intervals] through the attached schedule of quantity, source, index, price, currency and requested correction. Preserve and provide meter records, correction versions and the complete calculation. The undisputed amount and payment arrangements remain governed by the agreement; this objection is not presented as a universal suspension. We propose joint review followed by the agreed expert for unresolved calculations, reserving legal issues for the dispute mechanism.
4. Notice of grid curtailment
We notify operator instruction [identifier] for [dates/times], attaching the instruction and availability records. Actual metered volume and the reasoned affected-energy estimate are separated from our own technical outages. Please apply clause [reference] and confirm who pursues operator compensation. Any receipt will be recorded to prevent double recovery; this notice is not, by itself, proof of entitlement to all lost revenue.
5. Request to replenish or extend security
Under clause [reference], exposure at [date] is [amount and formula], while security [identifier] expires on [date]. Please replenish/extend it using the agreed instrument and deadline. We attach the calculation, triggering condition and beneficiary requirements. This request is separate from a draw, which must independently satisfy the issuer’s documentary conditions. Release conditions should be specified to avoid covering the same exposure twice without a contractual basis.
6. Submission concerning a change in law
We rely on instrument [number, publication and applicable date] concerning obligation [identifier], distinguishing adoption from application. The net-cost calculation, mitigation and comparison with the original assumption are attached. We request the renegotiation meeting under clause [reference] and propose [adjustment], separating temporary and permanent effects. No right to stop delivery is assumed; unaffected obligations and already matured payments must be addressed separately.
7. Request for the lender direct-agreement package
For financing project [identifier], please set out the lender’s requested rights: assignment, default notice, cure, contractual intervention and termination conditions. Identify contacts, periods and compatibility with licences and linked agreements. Any extended cure should be coordinated with buyer security and exposure limits. The direct agreement must not be described as an automatic transfer of permits or the system operator’s obligations.
8. Cure request and close-out preparation
For breach [facts, period and clause], we request cure within the contractual period running from communication of this notice, as evidenced by the attached delivery record. If cure does not occur, termination conditions will be assessed without an ambiguous premature declaration. Provide close-out data: volumes, replacement prices, avoided costs, payments, security and origin attributes. The formula and offsets require checking against double recovery; valuation objections and the proper dispute forum remain distinct.
Frequently asked questions
Is every PPA for renewable electricity?
No. The EU definition does not restrict every PPA to renewables and can cover existing generation. Specify the promised source and attributes separately for the project.
Can I leave when market prices fall?
There is no general exit right merely because the transaction becomes less attractive. Examine the agreement and, where applicable, statutory hardship conditions.
Is a grid stoppage automatically force majeure?
No. Assess the cause, obligation, foreseeability and clause, then separately consider redispatching rules and any operator compensation.
Is one PPA form mandatory for every project?
The templates on ACER’s list are voluntary. A chosen model does not replace checks of governing law, roles and project schedules; choosing an organised market also requires reviewing its own rules.
Does a financial PPA replace physical supply?
Not simply by being signed. Price-difference settlement and actual electricity supply are distinct arrangements requiring coordination.
Can you help renegotiate a signed PPA?
Yes. First examine existing obligations, notices, security and third-party rights, then propose coordinated amendments. Renegotiation does not automatically suspend performance.
For non-payment involving a foreign counterparty, see the cross-border notice and debt-recovery guide.
For authorisations and related work, see our energy-law services.
Sources and legal provisions: Regulation (EU) 2019/943, consolidated text: PPAs, balancing and redispatching; Recommendation (EU) 2026/917: PPA barriers and structures; Romanian Civil Code: binding force, hardship, force majeure and penalties; ACER: PPAs and the list of voluntary templates.
Turn commercial decisions into verifiable terms
Provide the offer, draft, technical schedules and negotiation points. The review can identify accepted risks, missing records and mechanisms requiring coordination before signing or amendment.
This material considers legislation and case law available up to 5 November 2026. The version applicable to the events or proceedings must also be checked for the particular case. This is general information.